1. |
Improvement, Maintainance & Beautification of Delhi-Samalaka Section of NH-1 from Km 8.200 to Km 29.300 in the state of Delhi
|
Project Director NHAI, PIU, G.T.Karnal Road ,Kundli- 131028, Distt.Sonepat |
Rs. 1.7 cr |
12.05.2006 |
11.01.2006 |
|
2. |
Widening Of Road No.16 (Aruna Asaf Ali Road) from 2/4 Lanes to 6 Lanes i/c construction of Footpath Drains & Extenion of Culverts etc. (RD0 to Rd4640)
|
Executive Engineer
PWD Division No.VII (NCTD),
RR Lines, Ring Road,
New Delhi
|
Rs. 6.03 Cr |
17.05.2002 |
31.03.2005 |
|
3. |
Construction ASH Bund and Allied Civil works for unit 7 & 8 at Tau Devi Lal Thermal Power Project , Panipat , Haryana
|
Chief Engineer/ Themal Design, HPGCL, SCO No.21, Sector-11, Panchkula |
Rs. 7.03 Cr |
21.04.2004 |
28.02.2005 |
|
4. |
Improvement of Central Verge on RTR Marg from Moti Bagh Crossing to NH-8 Crossing, New Delhi
|
Executive Engineer
PWD Division No.VII (NCTD),
SU-Block, Piitampura,
Delhi110043
|
Rs. 0.68 Cr |
16.10.2003 |
15.01.2004 |
|
5. |
Constructing Co.Education Sr.Secondary School at Prashant Vihar with PILE Foundation i/c Water Supply, Sanitary Installation, Internal Electrical and External Developement Works .
|
Executive Engineer
PWD Division No.28 (NCTD),
SU-Block, Piitampura,
Delhi110043
|
Rs. 3.19 Cr |
Jan, 2002 |
02.11.2003 |
|
6. |
Constrution of Road Work Part (a)
Relocation Of Industries At Udyog Vihar, Sect-4, DSIDC, BAWANA, DELHI
|
General Manager
BSBK Limited, Nandini Road, Bhilai
|
Rs. 12.16 Cr |
May, 2001 |
Aug, 2002 |
|
7. |
Raising the Height Of Tailing Dam At RAMPURA Agucha Mines, District Bhilwara (RAJASTHAN ) |
Additional Executive Director
(PROJECTS), Hindustan Zinc Ltd. Udaipur ,RAJASTHAN
|
Rs. 4.10 Cr |
Nov, 2000 |
May, 2002 |
|
8. |
Construction of JNV at Kalukheda Distt. Ratlam (M.P.) SH:C/o 2 Nos. Dormitaries, 6 nos. Type-III, 1 No., Type-II and 6 nos, Type-I i/c Water Supply, Sanitary installation & Drainage Work
|
Executive Engineer
Indore Central Division No.1,
C.P.W.D., Indore (M.P.)
|
Rs. 1.14 Cr |
Nov, 1999 |
Oct, 2001 |
|
9. |
Construction of Four Laning and Strengthning of NH-1 from Km 155 to Km 212.166 (Lot HR-II) a World Bank Aided Project in the State of Haryana
|
A Joint Venture of Unitech Ltd. & LGC South Korea
H.O.: New Delhi
|
Rs. 20.99 Cr
|
April, 1995
|
May, 2000
|
|
|
|
|